Ladakh Renewable Energy Initiative

Hydro

Project Area / Name Project Description No. of Projects Status
Turtuk, Chulungkha, Bogdang, Tsati, Henache, Chamshen MHP Projects under execution stage, Civil, Penstock and E&M alloted works separate 6 Likely to be commissioned by end 2019
Waris, Shayok, Sumdhado, and Durbuk MHP Projects under execution stage, Turnkey works 4 Likely to be commissioned by end 2019
Rongdo (2×1500 KW) is under tendering stage MHP are under execution stage on Turnkey basisy 1 Likely to be allotted by April-May 2014, Commissioned within 3 years
Leh District Projects below 200 kW for which LREDA has prepared projects 5 Likely to be commissioned by end 2020

Upcoming Hydro Projects

Sasoma 10 MW Capacity Time line for preparation of DPR 30-09-2018 Estimated time of Project Completion 30-12-2022
Rongdo 10 MW Capacity Time line for preparation of DPR 30-09-2018 Estimated time of Project Completion 30-12-2022
Tia 0.6 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Temisgam 0.5 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Shayng 0.3 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Kubet 0.3 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Dha 0.6 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Kumdog 0.2 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Mangyu 0.5 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Kumdog 0.2 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Agyam 0.3 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021

Solar PV

Leh District SPV Power
Plants of 5 to 100 kWp with battery
support for villages with minigrids
(for the purpose of village electrification)
CFA Under LREI: 100%
40 Nos Total Aggregate Capicity (MW) 1.4 MW (Completed)
Leh District 5 kWp to 10 kWp
SPV power plants for institutions like
health centers, religious institutions,
education institutions
CFA Under LREI: 100%
60 Nos 500 kW (Completed)
Leh District 100 kWp SPV Power Plants in
defence establishments to meet
the day load requirements
CFA Under LREI:
100%
20 Nos 850 kW (Completed)
Leh District 1800 kWp SPV pumps in co-operative societies and farms 5 Nos Tender document has been prepared and will only be floated if beneficiaries are identified.
Currently cost to beneficiary for the SPV pumping system including high boring costs in Ladakh has not allowed for execution of the project, though demand for SPV Pumps is considerable in Leh District. Discussion on the same may be carried out during the steering committee meeting (Completed).

Solar thermal

Leh District Solar Green Houses (Domestic) Sanctioned 2500 Eecuted 2500
Leh District Solar Green Houses (Commercial) Sanctioned 750 Executed 750
Leh District Solar Water Heating Systems (100 LPD) Sanctioned 6000 sqm. Executed 6000 sqm.
Leh District Solar Water Heating Systems (200 LPD and above) Sanctioned 14,384 sqm. Executed 14,384 sqm.
Leh District Dish Type Solar Cookers (SK 14) Sanctioned 4500 units Executed 4500 units
Leh District Scheffler Steam Solar Cookers Sanctioned 15 systems Executed 15 systems

Other

Leh District Upgradation of Water Mills (Mechanical) implemented in yr 2012 Target 50 Completed
Leh District Pico Hydro Projects – Electrical (5 kW Capacity) 15 6 No’s Completed
Leh District Upgradation of Water Mills (Rantak) Sanctioned in 2017 150 LREDA has sent back the sanctioned amount and requested for a new sanction with only mechanical upgradation as there is only a very small demand for electrical upgradation

Solar Wind Hybrid Systems

Leh District Tharuk Residential School Completed Joint Meeting held with MNRE, LREDA and RMS Automation Systems in order to resolve the issues.
Leh District Nyoma Residential School Completed Company committed to resolving issues in 2017, providing local manpower in Leh and rectifying all problems
Leh District Puga Residential School Completed Company committed to resolving issues in 2017, providing local manpower in Leh and rectifying all problems.
Leh District Khaltse Residential School Completed Company has rectified issues.
Leh District Diskit Residential School Completed RMS Automation has received NOCs from various Institutions for completion of the Installation and rectification.
Leh District Solar Energy Park Completed No Payments has been released yet to the company.

Hydro

Sasoma 10 MW Capacity Time line for preparation of DPR 30-09-2018 Estimated time of Project Completion 30-12-2022
Rongdo 10 MW Capacity Time line for preparation of DPR 30-09-2018 Estimated time of Project Completion 30-12-2022
Tia 0.6 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Temisgam 0.5 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Shayng 0.3 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Kubet 0.3 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Dha 0.6 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Kumdog 0.2 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Mangyu 0.5 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Kumdog 0.2 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021
Agyam 0.3 MW Capacity Time line for preparation of DPR 30-07-2018 Estimated time of Project Completion 30-12-2021